House Cost

Plan

    Build timeline

    All subcontractorsOwn crew + licensed subs

    Sub durations include the idle days to schedule each new trade in. Crew durations come from crew hours ÷ crew size, and run alongside the licensed subs in the same phase. Permits come before week 0.

    Cost by phase

    Site overhead (supervision, temp services, bins, crew truck) is spread across phases by duration. Share = share of the total build cost in that scenario. Click a phase to see its line items.

    Price stack

    Share = share of the cost to build. Margin and sales tax sit on top of it and shrink when it shrinks.

    Who does what

    Line items

    Unit prices (editable)

    2026 estimates for the Ottawa–Gatineau region, not quotes. Sub labour is what a subcontractor charges, including their overhead and margin. Crew h is own-crew hours per unit; the default is the sub's wage cost (80% of their price) at $66/h. Edited rows are highlighted and saved.